Completion Date of Kampot Tourism Port Postponed Again, says MPWT Spokesman

After many delays since late 2020, the completion date of the US$8 million Kampot tourism port that was set for late this year could be delayed once again due to shortages of labour and construction materials caused by the COVID-19 crisis.

Ministry of Public Works and Transport (MPWT) spokesman HE Vasim Sorya said that a working team from the ministry in charge of the project has inspected the progress of construction earlier this week, but he has yet to receive the report on the inspection.

“In the context of COVID-19, the construction progress was interrupted, the number of workers has been reduced, so the completion of the project may be delayed,” said HE Vasim Sorya.

Based on the estimated data, the construction of this port to date is only about 75% complete, which is far behind the schedule.

However, June has passed but the project is not completed yet. The new deadline is set for late 2021, but it could be delayed further.

Located in Toek Chhu district, the ground was broken on the project in August 2018 and is being built under a US$8 million loan from the Asia Development Bank (ABD). (Read more)

Once operational, the 300-metre-long port will allow the docking of tourism vessels, which can carry up to 300 to 400 passengers.

The Kampot international tourism seaport will be the main gateway connecting tourism vessels from Thailand and Vietnam to Cambodia’s Kampot province.

- Video Advertisement -

Related Post

Advancing Regional Logistics: MPWT and YCH Group Review Progress on the Cambodia SuperPort Project

Strategic Collaborations Focus on Access Road Connectivity and Multimodal Transport Efficiency to Boost Cambodia’s Industrial Supply Chain Efforts to elevate Cambodia’s logistics and industrial sectors achieved a significant milestone as Her Excellency Koy Sodany, Permanent Secretary of State at the Ministry of Public Works and Transport, received a delegation from YCH Group, led by Project […]

Cambodia and World Bank Partner on $270 Million Road Infrastructure Project to Boost Community Employment

Prime Minister Hun Manet announces an accelerated 18-month infrastructure initiative utilizing community-contracted labor to construct roads and stimulate local livelihoods in Pursat province. Cambodia and the World Bank have officially agreed on a $270 million infrastructure funding package dedicated to road construction and regional development over an 18-month period. The announcement was made by Prime […]

Joint-Venture Cambodia SuperPort Breaks Ground on $300 Million SEZ in Kampong Speu

Developed by Singapore’s YCH Group and Cambodia’s Sear Brothers Investments, the 132-hectare dry port and industrial complex aims to modernize supply chains and elevate regional trade competitiveness Cambodia has officially commenced construction on a $300 million dry port and Special Economic Zone in Kampong Speu province, marking a major milestone in the Kingdom’s transport and […]

Japan-Funded 20,000-Hectare Southwest Phnom Penh Irrigation Scheme Nears 99% Completion

Inspected by Water Resources Minister Thor Chetha, the major JICA infrastructure project across Kampong Speu, Kandal, and Takeo promises to boost rice yields for nearly 8,000 farming families Agricultural productivity and flood management southwest of Cambodia’s capital are set for a major transformation as the Rehabilitation and Improvement of Irrigation and Drainage Systems Project in […]

Bassac and Prek Koy Riverbank Protection Projects Achieve 100% Completion Across Kandal and Kampong Cham

Cambodia’s water infrastructure development achieved a key milestone as two major riverbank protection projects along the Bassac River and Prek Koy stream reached 100% completion across Kandal and Kampong Cham provinces. An inter-ministerial working group led by HE Sot Rasmei, Secretary of State and Chairman of the Procurement Committee at the Ministry of Water Resources […]

Jinding Air Liquefaction Breaks Ground on $10 Million Industrial Gas Plant in Kampong Speu

Cambodia’s industrial supply chain achieved a major milestone with the official groundbreaking of the nation’s first large-scale industrial gas production facility in Kampong Speu province. Valued at over $10 million, the flagship project developed by Jinding Air Liquefaction (Cambodia) Co., Ltd. officially commenced construction on July 2, 2026, during a ceremony presided over by Kampong […]